WLSP Finishing Details

Week of 9/2: The crews will stripe the road including center line and fog lines. The landscapers will begin planting trees/shrubs/ground cover in the planter areas. Crews will also begin adjusting the utility lids and castings to the new level of the asphalt.

Week of 9/9: Installing guard rail, continue adjusting utilities, and continue planting

Week of 9/16 and week of 9/23: Private utility crews will begin adjusting their utility lids and castings (this will take around 2 weeks. General contractor will continue finishing up items listed above and begin punch list items.